How Much Does a Permit Cost?

One of the questions that often arises has to do with the cost of permits, as well as how long the permitting process takes. We recently submitted a plan for a home in Talking Rock that was a little over 3,000 livable square feet with a good-sized two-car garage. The Plan Submittal Fee to Yavapai County was $437.50. This is what the local jurisdiction collects up-front to cover their time to review your plans.

Initial review with Yavapai County was about two weeks. After a few days of slight modifications, the plans were resubmitted and the permit was approved. The total time was 28 calendar days. Not bad!

The cost to now pull the permit is $6,366.71 for the house and garage, and $287.50 for the grading. Thus, the total permit cost is $7,091.71. This amount includes impact fees.

We will be soon submitting another home in Talking Rock for permit. It is somewhat larger so I will use this blog to let everyone know how that goes.